Guangdong Province Hazardous Waste Comprehensive Treatment Demonstration Center Phase I Incineration Project Adjustment Environmental Impact Public Participation Second Public Announcement


Publish time:

2020-05-22

In accordance with the requirements of the "Environmental Impact Assessment Law of the People's Republic of China", the "Measures for Public Participation in Environmental Impact Assessment" (Ministry Order No. 4), etc., it is necessary to carry out public participation in the environmental impact assessment of the Phase I Incineration Project Adjustment of Guangdong Provincial Hazardous Waste Comprehensive Treatment Demonstration Center (hereinafter referred to as "this adjustment project") to understand the public's attitude towards the construction of this adjustment project and their opinions and suggestions on environmental protection aspects of this adjustment project, and to accept public supervision.

Guangdong Province Hazardous Waste Comprehensive Treatment Demonstration Center Phase I Incineration Project Adjustment Environmental Impact Public Participation Second Public Announcement

Abstract:

  In accordance with the requirements of the "Environmental Impact Assessment Law of the People's Republic of China", the "Public Participation in Environmental Impact Assessment Measures" (Ministry Order No. 4), etc., it is necessary to carry out public participation in the environmental impact assessment of the Phase I Incineration Project Adjustment of Guangdong Provincial Hazardous Waste Comprehensive Treatment Demonstration Center (hereinafter referred to as the "Project Adjustment"), in order to understand the public's attitude towards the construction of the Project Adjustment and their opinions and suggestions on environmental protection, and to accept public supervision.

  I. Project Name and Overview

  (1) Project Name: Environmental Impact Report for the Adjustment of Phase I Incineration Project of Guangdong Provincial Hazardous Waste Comprehensive Treatment Demonstration Center

  (2) Construction Unit: Huizhou Dongjiang Veolia Environmental Service Co., Ltd.

  (3) Construction Address: Shiwuliao Forest Farm, Lianghua Town, Huicheng District, Huizhou City, Guangdong Province (Geographical location: East longitude 114°37′, North latitude 23°05′).

  (4) Project Overview

  (1) Existing Project and its Environmental Protection Status

  The existing project has completed and put into operation one incineration line, and the main pollutants generated are waste gas, wastewater, noise, and solid waste. According to the acceptance report and routine monitoring reports, after the treatment of various pollutants with corresponding measures, they can all meet the emission standards and have little impact on the surrounding environment.

  (2) Overview of this Construction Content

  This adjustment of the Phase I incineration project is adjusted relative to the current situation: adjusting the annual disposal capacity of the licensed operating categories, increasing the categories from 12 to 25 (the specific disposal categories of the Phase I incineration project after this adjustment are as follows: HW02 pharmaceutical waste, HW03 waste drugs, medicines, HW04 pesticide waste, HW06 waste organic solvents, HW07 heat-treated cyanide-containing waste, HW08 waste mineral oil, HW09 emulsion, HW11 distillation residue, HW12 paint waste, HW13 organic resin waste, HW16 photosensitive material waste, HW17 surface treatment waste, HW18 incineration disposal residue, HW21 chromium-containing waste, HW33 inorganic cyanide waste, HW34 waste acid, HW35 waste alkali, HW37 organophosphorus compound waste, HW38 organic cyanide waste, HW39 phenol-containing waste, HW40 ether-containing waste, HW45 waste containing organic halides, HW48 non-ferrous metal smelting waste, HW49 other waste, HW50 waste catalyst, a total of 25 categories), the annual disposal scale remains unchanged (20000t), the waste liquid storage tank is cancelled (after the completion of the Phase II project of the demonstration center, it will rely on the Phase II waste liquid storage tank, and then this waste liquid storage tank will be cancelled), and the collection and storage of mercury-containing waste HW29 (900-023-29) is added; other contents remain unchanged.

  II. Potential Environmental Impacts and Environmental Protection Measures of the Project

  Waste gas: After the completion of this adjustment project, the main waste gases of the demonstration center include incineration flue gas generated by the incineration system, waste gas from the hazardous waste temporary storage warehouse, waste gas from the tank area, and waste gas from the material pit. The incineration system flue gas is treated by a comprehensive system of "waste heat boiler SNCR denitrification + rapid cooling acid removal desulfurization tower + Venturi tube (dry acid removal + activated carbon adsorption) + bag dust remover + alkali washing + flue gas heater", reaching the atmospheric pollutant emission limits of the "Standard for Pollution Control of Hazardous Waste Incineration" (GB18484-2001), and discharged into the atmosphere through a chimney. The waste gas from the temporary storage warehouse and the tank area is purified by "alkali absorption + activated carbon adsorption" measures and discharged through the exhaust pipe. The waste gas from the material pit in the main plant is collected under negative pressure and sent to the rotary kiln incineration system for incineration and disposal.

  Wastewater: The wastewater generated after the completion of this adjustment project mainly includes production wastewater, domestic sewage, and initial rainwater. After treatment by the existing Phase I wastewater treatment facilities, it meets the stricter requirements of the "Water Quality for Industrial Water Reuse in Urban Sewage Reuse" (GB/T19923-2005) and the "Water Quality for Urban Miscellaneous Water Reuse in Urban Sewage Reuse" (GB/T18920-2002), and is all reused for processes such as rapid cooling tower spraying, alkali washing tower water replenishment, and greening, and is not discharged externally.

  Noise: After noise reduction, sound insulation, and noise reduction measures, the noise impact on the surrounding environment can be reduced.

  Solid waste: Solid waste generated during the production process of this adjustment project includes fly ash, slag, waste gas treatment waste (waste activated carbon, waste bags), concentrated crystalline salt, waste resin replaced by ion exchange in the soft water preparation process, and office and domestic garbage. Fly ash is relied on the on-site stabilization/solidification treatment workshop, stabilized and solidified, and finally sent to a safe landfill; slag is directly safely landfilled; concentrated crystalline salt is packaged in a special anti-seepage package and landfilled separately in a specific area. Waste gas treatment waste (waste activated carbon, waste bags) and waste resin replaced by ion exchange in the soft water preparation process are returned to the incinerator of this adjustment project for incineration and disposal. Office and domestic garbage is incinerated in the incinerator. After the above effective treatment measures, the solid waste generated during the operation period has little impact on the environment.

  Risk: This adjustment project has formulated environmental risk prevention measures for the entire process of hazardous waste treatment and disposal, covering hazardous waste collection and transportation, temporary storage, feeding, and incineration. The construction unit entrusts a professional hazardous waste transportation company to collect and transport the hazardous waste disposed of by this adjustment project to prevent the risk of hazardous waste collection and transportation; uses closed barrels to temporarily store waste, which can prevent the risk of hazardous waste temporary storage; establishes a professional laboratory to study compatibility plans, which can prevent the risk of hazardous waste compatibility; uses semi-automatic feeding facilities, and all operators have undergone on-the-job training, which can prevent the risk of hazardous waste feeding; the incineration equipment is equipped with a professional emergency system and a linkage reaction mechanism, and high-specification equipment designed with refractory materials is selected. Through comprehensive analysis, after taking corresponding preventive and emergency measures, the environmental risk level of this adjustment project is acceptable.

  III. Conclusion

  The construction unit must strictly abide by the "three simultaneous" regulations, implement the environmental protection measures proposed in this report, ensure the normal operation of environmental protection facilities, and strengthen environmental management and monitoring systems. From the perspective of environmental protection, the project construction is feasible.

  IV. Network Connection of the Draft Environmental Impact Report and Methods and Channels for Reviewing the Paper Report

  Network connection: http://t.cn/A62UqWGe

  Paper report: Contact the construction unit. Contact information can be found in Section X.

  V. Public Scope and Main Matters for Soliciting Opinions

  (1) Scope: Units and individuals directly or indirectly affected by this adjustment project, as well as units and individuals concerned about the project construction.

  (2) Main Matters:

  1. Do you understand the construction of this adjustment project?

  2. What role do you think this adjustment project plays in the treatment of hazardous waste in the surrounding area?

  3. What do you think is the impact of this adjustment project on the social and economic aspects of this region?

  4. What do you think are the main environmental impacts of this adjustment project during its operation period?

  5. Do you think that after taking corresponding environmental protection measures, this adjustment project can reduce the impact of the pollution generated on the surrounding environment?

  6. What is your attitude towards the construction of this adjustment project?

  7. What suggestions do you have for this adjustment project in terms of environmental protection?

  VI. Network connection of the public opinion form

  Public opinion form URL: http://t.cn/A62UqpPV

  VII. Ways and channels for submitting public opinions

  The public can submit public opinions through letters, faxes, emails, etc.

  VIII. Start and end time for public opinion submission

  Public notice for 10 working days from today.

   IX. Name of the environmental impact report preparation unit : Guangdong Debao Environmental Technology Research Co., Ltd.

  X. Name and contact information of the construction unit

  Construction unit: Huizhou Dongjiang Veolia Environmental Service Co., Ltd.

  Contact person: Ye Gong Contact number: 0752-8964100-8702 Email: Huizhou.Project@veolia-es.cn

  Mailing address: Shiwuliao Forest Farm, Lianghua Town, Huichong County, Huizhou City, Guangdong Province

 

Huizhou Dongjiang Veolia Environmental Service Co., Ltd.

May 22, 2020

Tags: