2024 Anjia Tai Environmental Monitoring Project Procurement Inquiry


Publish time:

2023-12-18

2024 Anjia Tai Environmental Monitoring Project Procurement Inquiry

I. Price Inquiry / Quotation Document Request / Submission Method:

1 Contact Person / Supervisor

Business Contact: Zhong Yu Xiao ;     Email: yuxiao.zhong@veolia.com

Tel       Phone: 0752-8964100 ;      Fax     Number: 0752-8964152 。

Technical Contact: Xiao   Jie ;         Email: jie.xiao@veolia.com 。

Tel       Phone: 0752-8964100 ;      Fax       Number: 0752-8964152 。

 

Business Supervisor: Xu   Chun   Hua ;    Email: chunhua.xu@veolia.com 。

Tel       Phone: 0752-8964100 ;     Fax     Number: 0752-8964152 。

Technical Supervisor: Yang   Yun   Bo ;    Email: yunbo.yang@veolia.com 。

Tel       Phone: 0752-8964100 ;      Fax       Number: 0752-8964152 。

2 Address: Shiwuliao, Lianghua Town, Huidong County, Huizhou City, Guangdong Province (Postcode: 516323 ).

3 Quotation document submission deadline: 2023 Year 12 Month 21 Day afternoon 17 o'clock before

4 The quotation document must be sealed and delivered, with the offeror's seal affixed to the seal.

5 Composition of quotation documents (see attachment for detailed quotation document format 1 )

II. Quotation Content and Requirements:

1 Product price list;

2 Technical report on quoted goods;

3 Typical customers;

4 Quotation qualification documents (unit basic information: copy of business license, copy of opening permit, brief introduction of unit basic information, manufacturer's sales authorization certificate, quality assurance system 9001 certification documents (if any) and other relevant qualification certificates).

III. Summary of Commercial Terms:

1 Delivery location: Guangdong Anjiatai Environmental Protection Technology Co., Ltd., Shiwuliao, Lianghua Town, Huidong County, Huizhou City, Guangdong Province.

2 Quality Assurance:

The supplied goods must fully comply with the quality standards agreed upon by both parties.

3 Changes:

Within the validity period of the quotation, if the purchased goods cannot be provided due to reasons such as supplier's production suspension, the seller must use new services of the same or higher grade, and the prices of all services (unit price and total price) shall not be increased.

4 Acceptance Method:

Acceptance standards, methods and deadline for raising objections: Acceptance shall be carried out in accordance with the quality requirements and technical standards agreed upon by both parties. If the acceptance shows that the quality, specifications or performance of the goods fail to meet the standards stipulated in this contract in any material aspect, the supplier shall, after written notification by the purchaser and verification by the supplier, replace the purchaser with other qualified goods at the supplier's own expense, or the purchaser shall deduct the payment in the manner agreed upon by both parties.

5 Payment Method:

Subject to the actual payment method confirmed through communication.

IV. Quotation and Quotation Document Preparation Requirements:

1 The quotation includes product transportation, services, taxes and fees;

2 Each page of the quotation document must be stamped with the offeror's seal, and the document should be stamped with a binding seal;

3 Two copies of the quotation document (original and copy).

V. Definition of Invalid Quotation Documents:

The quotation document shall be invalid if any of the following circumstances occur:

1 The offeror is found to have engaged in illegal or irregular conduct that affects the fairness of the procurement process;

2 Due to force majeure, the buyer's procurement plan is cancelled.

3 The content of the quotation document does not meet the requirements of Clause IV of this quotation document.

VI. Quotation Document Review:

The buyer's review team will follow the " Fair, just, scientific, and optimal ” " principle to review the quotation documents provided by the seller, comprehensively considering technical indicators, price, after-sales service commitments, etc., and negotiate with the pre-selected offerors to determine the contract awardee.

VII. Signing Notification:

1 The inquirer may increase or decrease the quantity, technical standards and scope of procurement of goods within a certain range before signing the supply contract;

2 After all clauses of the supply contract are agreed upon by both parties, the inquirer shall arrange the signing.

VIII. Modification and Clarification of the Quotation Document:

1 Quotation document submission deadline 3 working days before , The inquirer may modify or supplement the relevant content of the document, and send the scanned copy of the modified and supplemented content with the seal to the offeror by email;

2 Bidders should carefully review this inquiry document. If there are any questions, they should be sent by email to both the contact person and supervisor specified in this inquiry document 3 working days before the deadline for submission of bid documents (questions sent only to the contact person or supervisor will be invalid and will not be answered by the inquirer), and inform the contact person by telephone. The inquirer will respond by email within 1 working days of receiving the email or telephone notification (whichever is later).

IX. Ordering Scope, Technical Performance and Parameters ( See attachment 1 )

Explanation:

The supplier must provide quotations for both Huidongwei and Anjiatai projects simultaneously and send them separately in sealed express mail.

 